A realistic kitchen remodel timeline, week by week

Demo to final walkthrough: how a full kitchen remodel actually sequences, where delays come from, and how to keep your project moving.

Remodeled kitchen with light oak cabinetry

Most kitchen delays are not caused by the build — they are caused by decisions and lead times. Cabinets, appliances, windows and stone slabs are all ordered items, and a single late selection can stall an otherwise clean schedule.

Before demo: selections and ordering

Layout is locked, cabinetry is ordered, appliances are confirmed with real specs, and plumbing and lighting are chosen. We do not start demolition until long-lead items have shipping dates.

Weeks 1-2: demo and rough-in

Cabinets and flooring come out, walls open where needed, and electrical, plumbing and any structural work goes in. Inspections happen at the end of rough-in.

Weeks 3-4: close-up and cabinets

Insulation, drywall, paint prep, flooring, then cabinet installation. Once boxes are set and leveled, the countertop template can be made — stone fabrication typically follows about a week later.

Weeks 5-6: finishes and punch list

  • Counters, backsplash tile and sink
  • Appliance installation and hookups
  • Trim, hardware, paint touch-up and lighting
  • Final inspection and a written punch list

How to protect your schedule

  • Make every selection before demo day
  • Approve change orders in writing and immediately
  • Order appliances early — they are the most common holdup
  • Keep one decision-maker on the homeowner side